New York Times on the Web Forums Science
Technology has always found its greatest consumer in a nation's
war and defense efforts. Since the last attempts at a "Star Wars"
defense system, has technology changed considerably enough to make
the latest Missile Defense initiatives more successful? Can such an
application of science be successful? Is a militarized space
inevitable, necessary or impossible?
Read Debates, a
new Web-only feature culled from Readers' Opinions, published every
Thursday.
(1857 previous messages)
lchic
- 08:24pm Apr 28, 2002 EST (#1858
of 1866) Mix a little GU.com with NYT.com - NET the wider
perspective!
LAXITY : Laxity cited in corrosion of reactor head at
Davis-Besse power plant
04/06/02 / John Funk / Plain Dealer Reporter / Oak Harbor,
Ohio
- The Nuclear Regulatory Commission yesterday sharply criticized
FirstEnergy Corp. officials for overlooking evidence of corrosion
that ultimately crippled the Davis-Besse nuclear power plant.
"Davis-Besse had several opportunities [in the last decade] to
clean and inspect the reactor head and did not do it," Jack Grobe,
director of reactor safety in the NRC's Midwest region, told an
audience of 500 from the auditorium stage at Oak Harbor High School.
Davis-Besse's top management listened from the other side of the
dais.
The corrosion created a large hole in the reactor's head that
left only three-eighths of an inch of stainless steel between the
inside of the reactor and the containment vessel it sits in - "an
unacceptable margin of safety," said Jim Dyer, the NRC's regional
administrator.
FirstEnergy officials have emphasized that the corrosion did not
lead to radiation leaks or pose a health hazard.
"We could have and should have found [the problems] earlier,"
Howard Bergendahl, FirstEnergy Nuclear Operating Co. vice president
at Davis-Besse, said in response. "We were mistaken. Our job is to
expect the unexpected. We did not do this."
NRC officials, addressing the public meeting held to disclose
preliminary results of their investigation, said this is only the
fact-finding phase. They left open the possibility that FirstEnergy
could face sanctions.
Davis-Besse, which is on Lake Erie about 22 miles east of Toledo,
has been shut down since Feb. 16 for refueling and an inspection
ordered by the NRC after similar plants developed cracks in critical
control-rod mechanisms.
The 45-minute report detailed what the NRC's special inspection
team found last month - both in Davis-Besse's records and on the
heavily damaged reactor head. The federal team agreed with company's
findings on the corrosion's cause: Boric acid leaked from the
reactor through the cracks and ate a 4-to-5-inch-by-7-inch hole
nearly through the 6½-inch-thick solid steel reactor cap.
The cap, or head, measures 17 feet in diameter and weighs 150
tons. It is lined with stainless steel, which is impervious to boric
acid. But the corrosion, going on at least since 1999, rusted out
about 35 pounds of the head's carbon steel, the NRC team calculated.
After the Davis-Besse corrosion was found, the NRC asked the
operators of all 68 reactors of similar design to submit inspection
records. So far, the Davis-Besse "wastage" is the only case of
significant corrosion.
FirstEnergy officials are proposing that the hole be sealed with
a stainless steel plug and that the plant be restarted by July while
it waits as much as two years for a new head it has ordered from
overseas. Some groups want the plant to stay closed until the new
head arrives. Others are calling for the plant's permanent closure.
The NRC must approve any changes.
Brian Sheron, NRC associate director of licensing, said that if
the commission had known what it knows now about Davis-Besse's past
inspections it would not have allowed Davis-Besse to operate six
weeks beyond a Dec. 31 inspection deadline.
FirstEnergy last fall persuaded the NRC that the plant could
safely operate until Feb. 16. The company wanted to run the reactor
until April 1, but the NRC wanted the control-rod mechanisms
inspected for cracks.
The NRC special team's findings include:
In 1990, Davis-Besse engineers proposed modifying the insulation
and service structure that hangs above the domed reactor head to
give workers room to clean and inspect the top of the reactor head.
The company never made the modifications. The structure, with
insulation on its bottom, is two inches from the head at its center
- making cleaning and inspecting difficult.
The Davis-Besse reactor was le
lchic
- 08:26pm Apr 28, 2002 EST (#1859
of 1866) Mix a little GU.com with NYT.com - NET the wider
perspective!
The Davis-Besse reactor was leaking boric acid for years. Acid
crystals were not removed from the very top of the head in a 1996
inspection because of the closeness of the insulation and service
structure. By 1998, boric acid crystals covered the head and had
turned from white to brown, indicating rust.
Boric acid crystals and ferrous oxide (rust) dust were so thick
in the reactor's containment building by May 1999 that the company
installed filters on its radioactive monitoring equipment. By
November 1999, the filters had to be changed every other day, and
cooling coils on air-conditioning equipment had to be cleaned
frequently.
In 2000, workers had to use crowbars and hot water to clean the
hardened "lava-like," rusty boric acid from the reactor top. Because
of the closeness of the insulation and service structure, they did
not clean the center of the head- where several sleeves for
control-rod drive mechanism were cracked and leaking.
"The delay in the modifications of the service structure played a
key role" in the corrosion, said Grobe.
"Davis-Besse staff assumed the extra boric acid was due to flange
leakage [a harmless leak high above the reactor head] and the color
due to the age of the deposits on the air coolers," he said. "The
NRC believes it was a sign of corrosion to the head."
FirstEnergy spokesman Todd Schneider said the modifications to
the service structure and insulation were on the company's work list
at several refueling outages but were pushed back because other work
had to be done and because no one in the industry at the time
believed such acid leaks were a safety problem.
"Looking back, it [the modification] might have helped us prevent
today's problems," he said.
Many in the audience were critical of the company and the agency.
"Why should we have any confidence in either FirstEnergy or the
NRC?" asked former NRC inspector Howard Whitcomb. He said the NRC
should not accept FirstEnergy's proposal to fix the corrosion with a
stainless steel patch. Instead, he said, it should idle the plant
for two years until a new reactor lid is made.
FirstEnergy has said it would cost $10 million to $15 million a
month to buy power during the outage.
Others spoke in defense of the company.
"Nuclear energy is the most efficient and the cleanest," said
Elizabeth Wharry, who lives 3½ miles from the plant. "If you listen
to this hysteria and try to close the plant, you'll be throwing the
baby out with the bathwater." © 2002 The Plain Dealer http://www.ohiocitizen.org/campaigns/electric/laxity_cited.htm
(7
following messages)
New York Times on the Web Forums Science
Missile Defense
|